top of page
Project Work Began August 24, 2023
New Door & Frame
Powder Coat Finish
Doors, New Stored
Powder Coat Finish
Door Frames, New Stored
Powder Coat Frames, Including Inside to Prevent Rust.
Demolition Saw
Saw used to cut old frames from concrete block construction.
3E New Door Rough In
Minor Stucco Damage will be repaired and Painted to Match Existing.
3E Door Rough In
Minor Stucco Damage will be repaired and Painted to Match Existing.
3W New Door Rough In
Minor Stucco Damage will be repaired and Painted to Match Existing.
2E New Door Rough In
Minor Stucco Damage will be repaired and Painted to Match Existing.
2E New Door Rough In
Minor Stucco Damage will be repaired and Painted to Match Existing.
2W New Door Rough In
Minor Stucco Damage will be repaired and Painted to Match Existing.
Unit 1 New Door Rough In
Minor Stucco Damage will be repaired and Painted to Match Existing.
Pool New Door Rough In
Window for light in stairway. Lock elevated for child safety. Minor Stucco Damage will be repaired and Painted to Match Existing.
Det Garage New Door Rough In
East Garage New Door Rough In
West Garage New Door Rough In
East Garage Complete
West Garage Complete
Detached Garage Complete
Unit 1 Complete
Unit 2 East Complete
Unit 2 West Complete
Unit 3 East Complete
Unit 3 West Complete
26-Pool.Cpt
bottom of page